All insights

New launch · Condo

New Condo Keys Late? What Liquidated Damages Mean for You

By · 9 minute read · Published 20 November 2026

By · CEA R073319H · Published 20 November 2026 · Last reviewed November 2026

Quick answer: If the developer is late, URA's Home Buyers' Guide says it is liable to pay liquidated damages. It must deliver vacant possession by the date in the S&PA and 21 days from receipt of the 25% payment due at TOP. A late Notice to Complete is a separate trigger. The rate is in your own S&PA, not in URA's guide. General information only, sources at the end.

Facts verified: 3 November 2026 · Sources listed below

This page is for buyers of a new launch condo that is still being built, and for buyers whose keys are late. By the end, you will know three things.

You will know which dates count. You will know when the developer owes liquidated damages, meaning a sum worked out under the contract formula. And you will know where to find the rate.

What a buyer can claim when the developer is late is set by the standard Sale and Purchase Agreement (S&PA) that licensed developers must use. This page sets out what URA's Home Buyers' Guide and Controller of Housing circulars say about it. It does not give a rate. The rate sits in the S&PA clause itself, and I could not confirm a figure on an official page I could open. For the payment side of the same timeline, see how progressive payments work.

Why the date and the clause matter

A new launch condo is sold before it is built. So the date on which you can collect the keys is a promise in a contract, not a fact. Delays happen.

URA also cautions that developers or their agencies may give an estimated Temporary Occupation Permit (TOP) date, based on the planned construction schedule. The actual TOP date may deviate from it depending on construction progress. The binding date is the one in your agreement.

URA's guide does not quote a liquidated damages rate. So the rate, what it is calculated on and the period it runs for are for you to read in your own S&PA.

What it looks like when it is handled properly

You know the vacant possession date in your Option to Purchase and S&PA, and you know the two separate triggers for liquidated damages. You have read the rate clause, or your lawyer has.

If your keys are late, you know the order URA's guide describes: discuss it with the developer first, then consider mediation, with legal advice on your rights under the S&PA.

Is this you?

  • You bought a new launch condo that is still being built, and the keys date is coming.
  • Your keys are late and you are not sure what happens next.
  • You were given an estimated TOP date and want to know if it is binding.
  • You want to know whether the developer owes you anything, and where the rate is written.
  • You heard about COVID 19 delay relief and wonder whether it applies to your project.

What the rules say, step by step

1. Know the dates that matter

URA's Home Buyers' Guide explains that the vacant possession date is the latest date by which the developer needs to hand over the keys. It is stated in the Option to Purchase and the S&PA. The developer is contractually bound to deliver vacant possession by that date. The actual hand over of keys may happen before or after it.

The guide adds that delivery of vacant possession happens after the TOP is issued for the project. If the legal requirements have been met, it can happen after the Certificate of Statutory Completion (CSC) instead. The milestones are compared in TOP, CSC and vacant possession explained.

Source: URA, Home Buyers' Guide, Stage 4, Vacant Possession Date, checked 3 November 2026. https://go.gov.sg/home-buyers-guide-full

2. Know when the developer owes liquidated damages

URA's guide says the developer is required to deliver vacant possession of the unit no later than:

It says the developer is liable to pay liquidated damages if it fails to deliver vacant possession by those dates. The guide refers to a formula in the S&PA and does not quote a rate.

Liquidated damages are a sum worked out under the agreed contract formula. Your own S&PA is where to read the rate, what it is calculated on, and the period it runs for. A clause by clause guide to the S&PA shows where to look.

Source: URA, Home Buyers' Guide, Stage 5, Delivery of Vacant Possession, checked 3 November 2026. https://go.gov.sg/home-buyers-guide-full

3. Know the second kind of delay: the Notice to Complete

Vacant possession is not the end of the timeline. URA's guide says the developer will issue a Notice to Complete by whichever is earlier: the date specified in the S&PA, or 3 years after delivery of vacant possession. Completion must then take place within 14 days after the buyer receives it.

The guide says the buyer has a right to claim liquidated damages according to the formula in the S&PA. This applies if the developer does not issue the Notice to Complete by the deadline in the S&PA. Late vacant possession and a late Notice to Complete are therefore two separate triggers in the contract.

URA's 2008 circular on the revised Housing Developers Rules also refers to liquidated damages payable to the purchaser. These are deductible from any instalment of the purchase price due to the vendor. Clause numbers and wording have been revised since, so read the clause in the version of the S&PA you signed.

Source: URA, Home Buyers' Guide, Stage 5, Procedure for completion of sale and Liquidated Damages, checked 3 November 2026. https://go.gov.sg/home-buyers-guide-full

Source: URA, Controller of Housing circular on the revised Housing Developers Rules (26 September 2008), Appendix 4, clause 16.7, checked 3 November 2026. www.ura.gov.sg/guidelines/archived-circulars/coh08-04/

4. Know about the COVID 19 relief that still appears in URA's pages

You may see references to delay relief from the COVID 19 period. URA's circular on the commencement of Part 8C of the COVID 19 (Temporary Measures) Act covers this. It says developers who could not meet the committed delivery date because of COVID 19 construction delays could serve a notice. The notice could extend the delivery date by up to 122 days.

Purchasers could then claim reimbursement of qualifying out of pocket costs, up to a cap of 70% of the liquidated damages originally payable under the S&PA. The circular says Part 8C and its regulations took effect on 1 July 2021.

It does not state an end date, so I cannot tell you whether the relief covers a given project today. Ask the developer's solicitors or URA.

Source: URA, Controller of Housing circular on Part 8C of the COVID 19 (Temporary Measures) Act, relief for delays, checked 3 November 2026. www.ura.gov.sg/guidelines/archived-circulars/coh21-01/

5. Know what else moves with delivery: maintenance charges and the defects clock

Two other dates move with delivery.

URA's guide says maintenance charges payable to the developer start on one of two dates:

The defects liability period is 12 months. It runs from whichever of these two dates is earlier:

The developer must make good defects within one month of receiving the buyer's notice. The defects liability period guide covers the unit side.

Source: URA, Home Buyers' Guide, Stage 5, Maintenance Fee and Defects Liability Period, checked 3 November 2026. https://go.gov.sg/home-buyers-guide-full

6. Know the steps if you and the developer disagree

URA's guide says that in a dispute, the buyer should first discuss it with the developer, and may consider legal advice on rights under the S&PA. It encourages direct negotiation, then mediation.

It lists the Singapore Mediation Centre, the Law Society mediation scheme, the REDAS Conciliation Panel for purchasers and developer members of REDAS, and the SISV Dispute Resolution Centre. For claims under $60,000, the guide says parties could use the Small Case Commercial Mediation Scheme. Above $60,000, they could use the Commercial Mediation Scheme.

The same guide also notes that a developer building 4 or fewer units is not required to be licensed under the Housing Developers (Control and Licensing) Act. It may use its own sales contract and is not subject to the same regulations. For such a purchase, URA says the buyer may wish to do more thorough due diligence and seek legal advice. The contract terms on delivery date and remedies matter even more there.

Source: URA, Home Buyers' Guide, Disputes; purchasing from developers with 4 or fewer units, checked 3 November 2026. https://go.gov.sg/home-buyers-guide-full

7. Know what a 2026 circular on developer conduct covers

On 22 May 2026, the Controller of Housing issued a circular on measures to strengthen protection of home buyers. It describes land sales disqualification and sales suspension for up to five years. These apply to developers with severe regulatory non compliances affecting safety, or consecutive projects with major defects.

The circular does not mention construction delays or completion timelines, so it is not a remedy for a late project. I include it because it shows where regulators have focused recently: safety and major defects.

Source: URA, Controller of Housing circular on new measures to enhance protection of home buyers (22 May 2026), circular, checked 3 November 2026. www.ura.gov.sg/guidelines/circulars/coh26-01/

8. Know the questions to ask before and during construction

This is general information and not legal advice. A lawyer can read your S&PA and tell you how its clauses apply.

Frequently asked questions

What is the vacant possession date, and is it the day I get my keys?

URA's Home Buyers' Guide says it is the latest date by which the developer needs to hand over the keys. It is stated in the Option to Purchase and the Sale and Purchase Agreement. The actual hand over may occur before or after it.

When does a developer owe me liquidated damages for late delivery?

URA's guide says the developer must deliver vacant possession by the date in the agreement and 21 days from receipt of the 25% payment due at TOP. It says the developer is liable to pay liquidated damages if it fails to do so.

What if the Notice to Complete is late?

URA's guide says the buyer has a right to claim liquidated damages. This is under the formula in the Sale and Purchase Agreement, if the developer does not issue the Notice to Complete by the deadline set in the agreement.

Can the developer extend my delivery date?

The Sale and Purchase Agreement sets the date. URA's circular on the COVID 19 (Temporary Measures) Act describes a period when developers could extend delivery by up to 122 days by notice. The circular gives no end date, so check whether it applies to your project.

Where do I find the liquidated damages rate for my condo?

In the standard Sale and Purchase Agreement that your developer must use. URA's Home Buyers' Guide refers to a formula in the agreement and does not quote a rate, so read your own clause or ask a lawyer.

What if I disagree with the developer about the delay?

URA's guide says the buyer should first discuss it with the developer, and may consider legal advice on rights under the Sale and Purchase Agreement. It encourages direct negotiation, then mediation.

Waiting for keys and not sure which clauses to check?

Tell Winfred which project you bought into. He can walk through the milestones URA describes, from vacant possession to the Notice to Complete, on a free 30 minute call, so you know which clauses to ask your lawyer about. General information only, not legal advice.

Next step: Property buyers guide · Free property evaluation

Ask Winfred on WhatsApp Book a free 30 minute call

Winfred Quek, CEA R073319H, Crestbrick Pte Ltd (L3010886H). General information as at 3 November 2026, not legal, financial, tax or property advice. Figures and rules are taken from the official pages listed in Sources & References and may change. This page makes no price or rent forecast.

Sources & References

Facts checked against the official sources below on 3 November 2026.